用户购买的道闸,厂家再发货前都会经过调试和检测,因此用户只要安装说明书正确的固定及接线即可。


The sluice purchased by the user will be debugged and tested before the manufacturer sends the goods again, so the user only needs to install the correct fixing and wiring instructions.


安装道闸时一定要将电源与控制线分开设在pvc∮25的线管。严格按强弱电分开布设的规范进行施工。


When installing the gate, it is necessary to separate the power supply from the control line in the pvc_25 line. Construction shall be carried out strictly in accordance with the specifications for the separation of strong and weak electricity.



哈尔滨道闸接线方法


道闸的电源地一定要与接地端接触好,保持与大地通畅,通讯线屏蔽层一端接地,可以与220V的地共在一起,但一定要保持接地端接地良好。


The power ground of the gate must be in good contact with the grounding end, keep smooth with the ground, and one end of the shielding layer of the communication line can be grounded together with the 220 V ground, but the grounding end must be well grounded.


哈尔滨挡车器」停车场道闸的接线方法及注意事项


Connection method and precautions of Gate Gate of "Harbin Blocker" Parking lot


1、 注意要按配件清单清点相关随机零配件。


1. Attention should be paid to the inventory of relevant random spare parts according to the list of spare parts.


2、根据所选用闸机左右向及安装现场实际情况,确定道闸主机的安装位置。


2. According to the left-right direction of the selected gate and the actual situation of the installation site, the installation location of the main engine of the gate is determined.



哈尔滨小区挡车器


对非混凝土地基或道闸主机安装有斜坡的情况,建议砌混凝土地基,并应确保地基与基础结合牢固,道闸主机机身与水平面垂直度小于1°。


For non-concrete foundation or sluice main engine installed with slopes, it is suggested that concrete foundation should be built, and the combination of foundation and foundation should be ensured. The verticality of sluice main engine fuselage and horizontal plane is less than 1 degree.


3、根据控制室或岗亭的位置,铺设电源线和控制线管(建议电源线和控制线分别穿在不同的线管中)。


3. According to the position of the control room or the guardhouse, lay the power line and the control line (it is suggested that the power line and the control line should be separately pierced in different lines).


4、在道闸主机安装位置安装膨胀螺钉(根据清单实际配备的配件确定),将道闸主机固定牢固后,方可使用。


4. Install expansion screw in the installation position of the main engine of the sluice (according to the actual fittings of the list), after fixing the main engine of the sluice firmly, it can be used.


5、用手要把将闸杆摇到水平位置,确定闸杆端部叉杆的安装位置,并用螺丝将叉杆固定牢固(无叉杆情况无需安装)。


5. Roll the brake rod to the horizontal position by hand, determine the installation position of the fork rod at the end of the brake rod, and fix the fork rod firmly with screw (no fork rod is required).


6、仔细对照接线图,将电源线和相关控制线接到闸机控制板上,确定无误后,拧紧调试。


6. Contrast wiring diagram carefully, connect power supply line and related control line to the control board of the gate, and tighten debugging after confirming that there is no mistake.


注:以上操作均应在断电的情况下进行。


Note: All the above operations should be carried out in case of power failure.


版权与免责声明:
1.凡本网注明"来源:全球供应商网"的所有作品,版权均属于全球供应商网,转载请必须注明全球供应商网。违反者本网将追究相关法律责任。
2.企业发布的公司新闻、技术文章、资料下载等内容,如涉及侵权、违规遭投诉的,一律由发布企业自行承担责任,本网有权删除内容并追溯责任。
3.本网转载并注明自其它来源的作品,目的在于传递更多信息,并不代表本网赞同其观点或证实其内容的真实性,不承担此类作品侵权行为的直接责任及连带责任。其他媒体、网站或个人从本网转载时,必须保留本网注明的作品来源,并自负版权等法律责任。 4.如涉及作品内容、版权等问题,请在作品发表之日起一周内与本网联系。